Department of Energy Logo
Sandia National Labs Logo

Port Angeles Landing Mall

Technology Type Lithium Iron Phosphate Battery
Rated Power 75 kW
Duration at Rated Power (HH:MM) 0:15.00 / 0.53
URL More about Port Angeles Landing Mall
The unit experienced a fire in July 2013. For details http://www.peninsuladailynews.com/article/20130709/NEWS/307099993 A nominal 50 kWh bank of Lithium-ion batteries packaged with a 75 kW inverter and open DR dispatch protocol was installed at a mall in downtown Port Angeles, WA. The storage bank can be charged or discharged via a remote signal by the local utility as a means for load shaping and Rapid Demand Response. The mall can also use the storage bank to peak shave when the storage is not used by the utility.
This data has been validated by project staff through a review of publicly available information about the project, and verified by the project owner. Information is accurate as of 2016-04-29.
Project Status
Status De-Commissioned
Commissioning On 04.01.2012
Decommissioned On 03.07.2013
Project Includes Multiple Systems No
Siting
Location

Landing Mall on the Front Street
Port Angeles, Washington 98362
United States

ISO/RTO N/A
Utility City of Port Angeles
Utility Type Public Owned
Paired Grid Resource Secondary Distribution
Project Includes Multiple Systems No
Ownership & Value Chain Partners
Ownership Model Third-Party-Owned
Equity Owner 1 Catalyst Energy Technologies, Inc.
Equity Owner 1 Percent 100%
Energy Storage Technology Provider International Battery
Power Electronics Provider EDA
Integrator Company Catalyst Energy Technologies, Inc.
O&M Contractor Catalyst Energy Technologies, Inc.
Developer Catalyst Energy Technologies, Inc.
Cost & Performance
Projected Project Lifetime 10 years
Performance Performance metrics not available
Capital Expenditure $165000
Benefits
Service Use Case Demand Response
Electric Bill Management
Electric Energy Time Shift
Renewables Capacity Firming
Renewables Energy Time Shift
Funding
Funding Source 1 Federal/National Government – RD&D
Bonneville Power Administration
$82550
Funding Source 2 State/Provincial/Regional Grant
City of Port Angeles
$8000
Funding Source 3 Private/Third Party Equity
The Landing Mall
$14550
Research Partner
Research Institution Bonneville Power Administration
Research Description Smart grid and peak load reduction

Export Data