Technology Type Vanadium Redox Flow Battery
Rated Power 2000 kW
URL More about Milton-IESO
The Milton site will be a four-hour flow battery, capable of two MW performance and eight Mwh of storage capacity. Energy storage has the potential to transform how the IESO plans and operates the power system by providing a range of real-time grid balancing services and injecting or withdrawing energy on demand
This data has been validated by project staff through a review of publicly available information about the project, and verified by the project owner.
Project Status
Status Contracted
Project Includes Multiple Systems No
Siting
Location

200 Chisholm Dr,
Milton, Ontario L9T 5E7
Canada

ISO/RTO IESO
Utility Type
Paired Grid Resource
Project Includes Multiple Systems No
Ownership & Value Chain Partners
Ownership Model Third-Party-Owned
Equity Owner 1 Baseload Power Corp
Energy Storage Technology Provider Gildemeister energy solutions
Power Electronics Provider  Baseload Power Corp
Integrator Company  Baseload Power Corp
Cost & Performance
Performance N.A
Benefits
Service Use Case Electric Bill Management
Export Data PDF

Print to PDF

You may use your computer system's built-in dialog to obtain a PDF of this page through the Print menu. Print this page, then choose Print to PDF or Save to PDF near the bottom of the dialog box.

Print and Save to PDF

Export Data

Thank you for using the Global Energy Storage Database. Please provide your e-mail address to download the data. Upon filling out the form you will receive an email with a link to the full data set you requested.

Suggest Update

Thank you for using the Global Energy Storage Database. Please provide the following information to help us research your update to this content.