Department of Energy Logo
Sandia National Labs Logo

EnerDel GRESS - FSK St. Petersburg

Technology Type Lithium-ion Battery
Rated Power 1500 kW
Duration at Rated Power (HH:MM) 0:15.00 / 1.67
URL More about EnerDel GRESS - FSK St. Petersburg
Multi-Functional Grid Energy Storage System (GRESS) installed on a substation in parallel with a gas turbine to provide peak shaving,load leveling and frequency support. EnerDel supplied the 2.5 MWh lithium ion unit which utilizes a Parker Hannifin Power Conversion System (PCS). An identical unit was installed to support Sochi during the 2014 Olympics: www.energystorageexchange.org/projects/1558
This data has been validated by project staff through a review of publicly available information about the project, and verified by the project owner. Information is accurate as of 2016-04-29.
Project Status
Status Operational
Commissioning On 01.10.2012
Project Includes Multiple Systems No
Siting
Location

Volkhov-Severnaya Substation
Saint Petersburg, Russia
Russia

ISO/RTO N/A
Utility Federal Grid Company of Russia
Utility Type Federally Owned
Paired Grid Resource Secondary Distribution
Paired Grid Resource Gas Turbine
Project Includes Multiple Systems No
Ownership & Value Chain Partners
Ownership Model Utility-Owned
Equity Owner 1 Federal Grid Company of Russia
Energy Storage Technology Provider EnerDel
Power Electronics Provider Parker Hannifin
Integrator Company EnerZ
Cost & Performance
Performance RTE 88%
Benefits
Service Use Case Electric Bill Management
Electric Supply Reserve Capacity - Spinning
Frequency Regulation
Microgrid Capability
Resiliency

Export Data