Ice Energy procurement from SCE's November 2014 LCR: 25.6 MW

Technology Type Ice Thermal Storage
Rated Power 25600 kW
Duration at Rated Power (HH:MM) 0:15.00 / 6.00
URL More about Ice Energy procurement from SCE's November 2014 LCR: 25.6 MW
Ice Energy has been awarded 16 contracts from Southern California Edison (SCE) to provide 25.6 MW of behind-the-meter thermal energy storage using Ice Energy’s proprietary Ice Bear system. Ice Energy was one of 3 providers selected in the behind-the-meter energy storage category, which was part of an energy storage procurement by SCE that was significantly larger than the minimum mandated by the California Public Utility Commission (CPUC). The contract resulted from an open and competitive process under SCE’s Local Capacity Requirements (LCR) RFO. The goals of the LCR RFO and California’s Storage Act Mandates are to optimize grid reliability, support renewables integration to meet the 2020 portfolio standards, and support the goal of reducing greenhouse gas emissions to 20% of 1990 levels by 2050. Ice Energy’s product, the Ice Bear, attaches to one or more standard 5-20 ton commercial AC units. The Ice Bear freezes ice at night when demand for power is low, capacity is abundant and increasingly sourced from renewables such as wind power. Then during the day, stored ice is used to provide cooling, instead of the power-intensive AC compressor. Ice Bears are deployed in smart-grid enabled, megawatt-scale fleets, and each Ice Bear can reduce harmful CO2 emissions by up to 10 tons per year. Installation is as quick as deploying a standard AC system.
This data has been validated by project staff through a review of publicly available information about the project, and verified by the project owner. Information is accurate as of 2016-04-29.
Project Status
Status Contracted
Project Includes Multiple Systems No
Siting
Location

Los Angeles, California
United States

ISO/RTO CAISO
Utility Southern California Edison
Utility Type Investor Owned
Paired Grid Resource
Project Includes Multiple Systems No
Ownership & Value Chain Partners
Ownership Model Third-Party-Owned
Equity Owner 1 Ice Energy
Cost & Performance
Projected Project Lifetime 20 years
Performance Performance metrics not available
Benefits
Service Use Case Electric Bill Management
Electric Energy Time Shift
Renewables Energy Time Shift
Export Data PDF

Print to PDF

You may use your computer system's built-in dialog to obtain a PDF of this page through the Print menu. Print this page, then choose Print to PDF or Save to PDF near the bottom of the dialog box.

Print and Save to PDF

Export Data

Thank you for using the Global Energy Storage Database. Please provide your e-mail address to download the data. Upon filling out the form you will receive an email with a link to the full data set you requested.

Suggest Update

Thank you for using the Global Energy Storage Database. Please provide the following information to help us research your update to this content.