Solar

The Pedro de Valdivia Thermosolar Plant, uses solar-cylinder parabolic concentration technology, is located in the municipality of María Elena, in the province of Tocopilla and in the region of Antofagasta. The thermosolar plant is composed of 2 phases of 180 MW, called Phase I and Phase II. Each phase is composed of 2 contiguous and independent plants of 90 MW each. The energy generated by the Pedro de Valdivia Thermosolar Plant will be injected into the SING, through two 220 kV double-circuit electric lines and one electric substation.


Molten Salt Thermal Storage


360,000

10:30.00