Reu

Ice Energy installed 1 MW of Ice Bear Thermal Energy Storage Assets as part of Redding Electric Utilities - Peak Capacity, Demand Response, HVAC Replacement Program. Redding Electric Utility used this procurement of thermal storage to avoid the high cost summer peak energy by shifting air conditioning load permanently to the night time hours when energy is more abundant and lower cost. The turnkey system costs $2170/kW.


Ice Thermal Storage


1,000

6:00.00